Gemini South Semester 2018A
The semester calendar shows multi-instrument queue nights, priority visitor nights, scheduled classical runs and engineering or commissioning blocks.
Horizontal rows represent instrument ports, color-coded to indicate instruments mounted.  Instruments are available for science unless otherwise noted.  
Note: ToO PIs should always check the "what's available now" pages that are linked from the contents list for the most up-to-date information. 
Scheduled classical runs are indicated by the last characters of the program ID, e.g., "C-1", whilst Priority Visitor programs are indicated with "PV".   
Engineering or commissioning blocks are shown across all rows when no backup queue is available (or telescope is closed).  
New and full moon dates are shown on the left and indicated in yellow and grey on the dates lines.  Dates above each month are color-coded to show weekends and holidays in red.
Key: GMOS   F2   visiting instr     Canopus   GSAOI   GPI   Cal unit  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28        
February Port 1 - up     GPI Camp.                    GHOST tests                   GSAOI                LP-2 February
- Port 2 cal                                                       -
15 new Moon Port 3 GMOS                                                     15 new
  Port 4 Canopus                                                      
  Port 5 F2                                                              
  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
March Port 1 - up   LP-2     GPI         GPI Campaign Q135                               GPI Campaign           March
1, 31 full Moon Port 2 cal                                                             1, 31 full
17 new Moon Port 3 GMOS                                                           17 new
  Port 4                                       IGRINS                      
  Port 5 F2                                                 DSSI          DSSI science block  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
April Port 1 - up GPI                GPI Campaign      Q-135                                           April
29 full Moon Port 2 cal                                                           29 full
15 new Moon Port 3 GMOS                                                         15 new
  Port 4                 IGRINS commissioning                                        IGRINS observations LP-17 and queue    
  Port 5 DSSI F2                                                            
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
May Port 1 - up GPI                                                             May
29 full Moon Port 2 cal                                                             29 full
15 new Moon Port 3 GMOS                                                           15 new
  Port 4 IG     Korean time and LP-17                                        IGRINS observations LP-17 and queue      
  Port 5 F2                                                              
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
June Port 1 - up GPI                       LP-12                                             June
28 full Moon Port 2 cal                                                           28 full
13 new Moon Port 3 GMOS                                                         13 new
  Port 4 IGRINS   LP-17 and queue                                               IGRINS observations LP-17 and queue      
  Port 5 F2                                                              
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
July Port 1 - up                                     GPI Campaign   GSAOI                July
27 full Moon Port 2 cal                                                             27 full
12 new Moon Port 3 GMOS                             GMOS stand down 12 new
  Port 4 IGRINS      LP-17 and queue         Canopus                                          
  Port 5 F2                                                 C-1, C-2            
version 28 Mar 2018